Winter construction measures for metal workshop building

Time:[2021-11-24]  Hits:2754

a. The winter construction of steel structure production and installation shall be carried out strictly in accordance with the relevant steel structure winter construction regulations.

b. When steel components are installed at positive temperature and at negative temperature, the shrinkage of components should be considered according to the difference in ambient temperature, and technical measures to adjust deviation should be taken during construction.

c. Welders who participate in the construction of negative temperature steel structures should undergo negative temperature welding process training, pass the examination, and obtain corresponding certificates.

d. The steel and related connecting materials used under negative temperature must be accompanied by a quality certificate, and the performance meets the requirements of the design and product standards.

e. The welding rod used under negative temperature shall not be exposed for more than 2 hours, and it shall be re-baked after more than 2 hours, and the number of baking of the welding rod shall not exceed 3 times.


f. Bake the flux according to the regulations before use, so that the water content does not exceed 0.1%.

g. High-strength bolts used under negative temperature must have a product certificate, and the torque coefficient and axial force must be re-inspected under negative temperature.

h. The paint used for steel structure under negative temperature shall not use water-based paint.

i. When the component is blanked, a shrinkage margin should be reserved, and the welding shrinkage and compression deformation should be coordinated with the shrinkage deformation of the steel under negative temperature.

j. When assembling the components, expand the assembly from the inside to the outside according to the order stipulated by the process, and do a test during the assembly of the negative temperature to determine the shrinkage value of the weld that needs to be reserved.

k. When assembling components, remove rust, burrs, soil, oil, ice and snow and other debris remaining in the joint 50mm, and keep the joints dry and free of residual moisture.

l. Multi-layer welding should be used when welding steel plates above 9mm under negative temperature. The welds should be welded layer by layer from bottom to top. Each weld is completed at a time. If the welding is interrupted, the welding defects should be removed before welding again. It is strictly forbidden to start the arc on the welding base metal.

m. When the steel structure is installed on site, in case of snow or wind speed above 6m/s, set up a protective shed.

n. The unqualified welds shall be removed and re-welded, and the welding shall be carried out in accordance with the provisions of the welding process of the steel structure under negative temperature.

o. When the ambient temperature is lower than 0°C, perform the painting process test before applying the anti-corrosion coating. When painting, the rust, oil stains, burrs, etc. on the surface of the component must be cleaned up, and the surface must be kept dry. No painting work is allowed in snowy weather or when there is thin ice on the components.

p. Take anti-skid measures when transporting and stacking steel structures in winter. The component stacking site is flat and solid without puddles, and the ground is free of icing. When the components of the same model are stacked, the components should be kept horizontal, and the shims should be placed on the same vertical line to prevent the components from slipping.

q. Before the steel structure is installed, its quality shall be re-inspected according to the requirements under negative temperature conditions, and the components that have been missed in the production and deformed during transportation and stacking shall be repaired and corrected on the ground.

r. When using steel cables to hoist steel components, anti-skid spacers should be added, the gusset plate that is hoisted at the same time as the components, and the fixtures required by the installer should be tied firmly with ropes.

s. According to the temperature conditions, the steel component installation sequence chart is compiled, and the installation shall be carried out in strict accordance with the specified sequence during construction.

t. Prepare the welding process for steel structure installation, and both ends of a component shall not be welded at the same time.

u. Before installation, remove ice, snow and dew on the surface of the components, but do not damage the coating.

v. Columns and main beams installed at negative temperature shall be corrected immediately, and the correct position shall be immediately fixed permanently. The components installed on the same day shall form a stable space system.

w. When installing high-strength bolt joints, there must be no snow or ice on the friction surface of the components, and no contact with dirt, oil and other stolen objects.

x.In addition to complying with the requirements of "Code for Construction and Acceptance of Steel Structure Engineering" (GB50250-95), the quality of steel structure installation under negative temperature should also be inspected and accepted according to design requirements.

Copyright:佛山市勝邦鋼結構有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粵ICP備13078463號
主站蜘蛛池模板: 制冷加热循环机,密闭高低温一体机,优质密闭低温冷冻机-无锡冠亚恒温制冷技术有限公司 | 徐州护栏,铝艺栏杆,铝艺大门,铝艺栏杆门,别墅铝艺大门-徐州桂丰金属科技有限公司 | 扭矩测试仪_拉力测试仪_扭力扳手测试仪_测试台-上海铸衡电子科技有限公司 | 铁氟龙膜/板/棒-铁氟龙网带/胶带/胶布-[东莞华氟]专注铁氟龙及特氟龙制品生产 | 木屑烘干机|酒糟烘干机|果渣烘干机_郑州东鼎机械 | 竖豆网-网站建设、小程序商城、软件定制开发 | 压滤机入料泵_渣浆泵_耐磨污水泵_保定森力克水泵制造有限公司 | 康明斯柴油发电机厂家-康明斯发电机(深圳)有限公司 | 景观造雾_人造雾设备_雾森系统_冷雾降温_雾化消毒_喷雾除尘厂家-成都景程雾森 | 欧美日韩人妻精品一区二区三区_欧美成人精品欧美一级乱黄_亚洲欧美日韩高清一区二区三区_国产一级做a爰片久久毛片_日韩一级视频在线观看播放_精品一区二区三区免费毛片爱_完整观看高清秒播国内外精品资源 | 重庆惠程信息科技股份有限公司| 全地形消防摩托车_背负式细水雾_全氟己酮灭火装置「斯库尔消防」 | 聚丙烯酰胺,聚合氯化铝,重金属捕捉剂,污泥调理剂,活性氧化铝,生石灰,反渗透阻垢剂,工业葡萄糖,硫酸铝,果壳活性炭,柱状活性炭,蜂窝活性炭,石英砂,锰砂-北京雁归来环保科技有限公司-以真诚为立足之本,以质量为生存之本,愿与海内外同仁共创双赢。雁归来人一路走来,气贯长虹,勇锐盖过怯弱,进取压倒苟安!我们紧扣时代脉搏,专注水处理、继往开来! | 天象文仪办公家具,25年一站式配齐经验厂家-办公家具官网 | 耐磨工业软管,PTFE耐腐蚀软管,耐磨喷砂胶管,超耐磨软管厂家,漯河利通液压管利通科技-耐磨工业软管,PTFE耐腐蚀软管,耐磨喷砂胶管,超耐磨软管厂家,漯河利通液压管利通科技 | 破碎机锤头-耐磨锤头-合金锤头-河南磐石耐磨材料有限公司 | 印刷公司,北京印刷厂,宣传画册手册印刷厂-和智印彩页设计 | 全自动高速点胶机,锡膏喷印机系列,点胶阀核心配件厂家-博宁 | 输送机|滚筒输送机|皮带输送机|滚筒|无动力滚筒|万向球生产厂家-上海霞韵输送机械设备有限公司 | 网咖网址导航,网咖分类目录,网址目录,免费收录国内外、各行业优秀网站网站。 | 网站建设_定制网站_高端网页设计开发_建站公司_深圳湉晨网络 | 深圳钢成培训专业从事,五轴培训,车铣复合培训,数控车床,CNC数控编程,模具编程 ,钣金机械与模具设计,powermill,mastercam,solidworks,ug,hypermill培训 | 智能搅拌锅_食品搅拌锅_多功能搅拌锅 - 青岛环速科技有限公司 | 欧艺宝盾科技(北京)有限责任公司_北京旋转门厂家_转门维修_高端商务门控定制 - | 售后服务认证-五星级物业售后服务体系认证证书-ISO27001信息安全管理体系认证证书查询认E云-湖北省贯标企业管理咨询有限公司 | 影像测量仪|检测设备定制|平面度测量仪|三坐标测量机|广州市海科思自动化设备有限公司-400-0528-668 | 泊头市特种油泵阀制造有限公司 - 渣油泵,重油泵,沥青泵,高压齿轮泵,煤焦油泵,导热油泵,三螺杆泵,圆弧齿轮泵,不锈钢齿轮泵, | 冷却塔厂家_冷却塔降噪维修_闭式冷却塔维修改造厂家-广东特菱空调 | 智慧网格,智慧城市,智慧社区,精准扶贫,农村电商,网格化,网格化管理,智慧养老,北京瑞光极远数码科技有限公司 | 暨南大学穗华口腔医院【官网】 | 乐云SEO | 品牌营销:抖音小红书关键词优化-ai搜索优化GEO推广 | 西安西雷脉冲功率技术有限公司-高压调制器/加速器与脉冲功率系统的研发/生产/应用推广/高压脉冲电源的应用研究/设计/生产和销售/高功率脉冲器件/材料与仪器设备的研发/生产和销售/高电压/大电流/强磁场环境的模拟及测试服务/会议会展服务/货物及进出口的业务/脉冲功率技术领域类的技术转让 | 四川迪瑞机电设备有限公司-容积式换热器|半容积式换热器|容积式换热机组|半容积式水加热器|换热器在线除垢防垢器|迪瑞机电 | 展馆展厅设计_数字多媒体展厅_3D全息投影_三维动画制作_企业宣传片|深圳市华南数字科技有限公司 斩天手游网_高质量手机游戏下载中心 | 液压升降货梯_导轨式升降机_往复式提升机_济南宇轩机械厂家 | 石家庄团建公司|石家庄拓展训练|石家庄拓展培训|石家庄公司团建|石家庄拓展公司-石家庄启聚团建公司 | 中国环博会 | 亚洲旗舰环保展 2025.4.21-23 上海新国际博览中心 中国焊接协会网站—中国焊接信息网;焊接行业最权威访问量最大的专业网站:焊接信息、焊接材料,焊接机器,焊接设备,焊机,焊材,辅助设备,焊机配件,仪器仪表,电动工具,钎焊,送丝机,表面处理,自动化专机,焊锡丝,助焊剂 | 全自动拆包机,自动拆包机,全自动逐层拆包机,全自动吨袋拆包机,吨袋拆包机,管链输送机,气流分级机 | 苏州氮气弹簧厂家_江浙沪氮气弹簧价格_江苏氮气弹簧规格_BelleFlex碟形弹簧_昆山三虑五金机械有限公司 | 酒类灌装机厂家_贴标机_灌装生产线-青州市锦德包装机械有限公司 酒店设计_建筑设计_室内装修装饰-北极点酒店设计公司 | 蒸汽流量计_涡轮流量计_涡街流量计_雷达液位计_污水流量计_分体式_大口径工业流量计-江苏长顺仪表 |